An analysis of power outage data shows that there was at least one unplanned outage in Nova Scotia nearly every day in 2024.

Over the year, there were more than 4,700 outages, recording just a single day without an unplanned outage.

The typical reliability standard is fewer than two outages per person per year, said University of Calgary energy economics professor Lucija Muehlenbachs.

“So I’d say it sounds like a tremendous number of outages in terms of frequency.”

  • vastard@lemmynsfw.com
    link
    fedilink
    arrow-up
    4
    ·
    12 days ago

    Ever-increasing fines for poor performance might finally be showing an effect. I’m not a Houston super fan but I do approve of his rhetoric of holding Emera responsible for its poor planning and lack of preventative maintenance.

    • HikingVet
      link
      fedilink
      arrow-up
      3
      ·
      12 days ago

      4700 unplanned outages doesn’t seem like progress.

      • vastard@lemmynsfw.com
        link
        fedilink
        arrow-up
        5
        ·
        12 days ago

        From a customer’s perspective it’s been frustrating and atrocious. But before the new fine structure was introduced they were allowed to do whatever the UARB would rubber stamp. Now at least there’s a penalty to sucking.

        • HikingVet
          link
          fedilink
          arrow-up
          3
          ·
          12 days ago

          It really doesn’t seem like they are improving.

          • vastard@lemmynsfw.com
            link
            fedilink
            arrow-up
            4
            ·
            12 days ago

            I agree. If the fine for not meeting the standard continues to increase every year eventually it will be too big to write off as a cost of doing business.

            I hate that I have a for-profit corporation for a utility.

            • HikingVet
              link
              fedilink
              arrow-up
              2
              ·
              12 days ago

              We have the same utility provider and I think it should be renationalized