Summary

France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.

The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.

President Macron hailed the launch as a key step for low-carbon energy and energy security.

Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”

    • einkorn@feddit.org
      link
      fedilink
      English
      arrow-up
      23
      arrow-down
      7
      ·
      2 days ago

      French nuclear energy is so heavily subsidised by the state that direct comparison seams hardly fair

    • Forester@yiffit.net
      link
      fedilink
      English
      arrow-up
      4
      arrow-down
      1
      ·
      2 days ago

      Don’t you understand line must go up, quarterly profits now consequences never .what the fuck is a long-term investment. Get that ideology out of my power plant this instant. /S