They’re planning to fill the underpass to support some temporary narrow center lanes. Then they’ll build the outer lanes proper before digging out the underpass and completing the inner lanes proper.

  • ericjmorey@beehaw.orgOP
    link
    fedilink
    English
    arrow-up
    3
    ·
    1 year ago

    They’re predicting that it will take 3 years to get the repairs finished proper. The backfill plan is definitely longer and more expensive. But, like you said, they will have the highway functional for the vast majority of that 3 years.