Rushing regulatory for a construction project where failures are as severe as they can potentially be with nuclear is beyond deranged.
Getting to the timelines you’re mentioning would require a mature nuclear industry with standardized builds, something which would take more than a decade to develop, at a steep premium.
Again, I support any investor willing to go there to do so, but there’s a good reason none do - these things quite simply do not pencil out.
regulatory: 3-5 years
site prep and build: 3-5 years
stocking, staffing, startup: 1-2 years
If we rush the regulatory, it’s then 4-7 years; or not even one decade.
I’m not saying it’s overnight, but it’s not ‘decades’.
Rushing regulatory for a construction project where failures are as severe as they can potentially be with nuclear is beyond deranged.
Getting to the timelines you’re mentioning would require a mature nuclear industry with standardized builds, something which would take more than a decade to develop, at a steep premium.
Again, I support any investor willing to go there to do so, but there’s a good reason none do - these things quite simply do not pencil out.